Requests For Proposals - 2

spacer

BIDDING REQUIREMENTS
Document 00120 – Notice to Bidders

Springfield Airport Authority
Abraham Lincoln Capital Airport

 

Sealed bids subject to the conditions and provisions presented herein will be received until 9:00 AM, Thursday September 10, 2015 and then publicly opened and read in the Offices of the Abraham Lincoln Capital Airport (The Airport), 1200 Capital Airport Drive, Springfield, IL  62707, for furnishing all labor, materials and equipment and performing all work necessary for:  ENTRANCE ROADS AND PARKING LOTS

A complete set of bid documents may be obtained from Springfield Reprographics, 1620 S. 5th Street, Springfield, IL  62703 (217) 523-4632, for a non-refundable fee of $25.00.

Contract Time
The Owner has established a contract performance time of 30 calendar days from the date of the Notice To Proceed.  All project work shall be substantially completed within the stated timeframe.  This project is subject to liquidated damages as prescribed within the Project Manual.

Bid Security
Each proposal must be accompanied by a bid guaranty in the amount of ten percent (10%) of the total amount of the bid. 

Bonding Requirements
The successful bidder will be required to furnish separate performance and payment bonds each in the amount equal to one hundred percent (100%) of the contract price at the time of contract execution.

Award of Contract
All proposals submitted in accordance with the instructions presented herein will be subject to evaluation.  Bids may be held by the Airport for a period not to exceed 75 days from the date of the bid opening for the purpose of conducting the bid evaluation.

Award of contract will be based on the lowest aggregate sum proposal submitted from those bidders that are confirmed as being responsive and responsible.  The Springfield Airport Authority reserves the right to waive any informality or irregularity in the bids received, to reject any or all bids in whole or part and to determine the lowest responsible bid.

The award of any contract resulting from this solicitation shall be made by the Board of Commissioners to the Lowest Responsive and Responsible Bidder.  In making this determination, the Springfield Airport Authority will take into account other factors in addition to the lowest dollar bid, such as the Springfield Airport Authority’s past transactions with the bidder, experience of the bidder, adequacy of equipment and personnel, ability to complete performance within a specified time limit and other pertinent considerations.

In the event a bidder has a complaint against the Springfield Airport Authority regarding the manner in which the proposal process has been handled, the complaint must be presented in writing to the Executive Director within forty-eight (48) hours of the opening of the proposals.  The Executive Director will notify the Chairman of the Board of Commissioners of the nature of the complaint.

Provisions:

Modification to the project documents may only be made by written addendum by the Owner or Owner’s authorized Representative.

The proposal must be made on the forms provided within the bound Project Manual.  Bidders must supply all required information prior to the time of bid opening.

Liquidated Damages are provided in the Proposal Form.

The Bidder must supply all information required by the Proposal Form.

Bids must be submitted on the specified Proposal Form and acceptance by the Sponsor shall constitute a Contract.

The proposal which is selected will be based on the lowest aggregate or combination of bids accepted.  The Owner reserves the right to select any one of the bids which best serves the Owner’s interest.

The Contractor is required to comply with wage and labor provisions and to pay minimum wages in accordance with the schedule of wage rates established by the State of Illinois for the county where the work is performed.  The highest rate will be the minimum rate paid for each work classification.

Submittal of Proposals
Additional information and instruction for submittal of a proposal are provided within the Instructions to Bidders.  Envelopes containing bids must be sealed and addressed to:

The Offices of the Abraham Lincoln Capital Airport
1200 Capital Airport Drive
Springfield, IL  62707

The upper left hand corner of the sealed envelope must identify the following information:

CONTRACT PROPOSAL
Bid of   (Name of Contractor)   
for construction improvements at Abraham Lincoln Capital Airport
To be opened at:  9:00 AM, Thursday September 10, 2015

 

spacer

BIDDING REQUIREMENTS
Document 00120 – Notice to Bidders

Springfield Airport Authority
Abraham Lincoln Capital Airport

 

Sealed bids subject to the conditions and provisions presented herein will be received until 9:30 AM, Thursday September 10, 2015 and then publicly opened and read in the Offices of the Abraham Lincoln Capital Airport (The Airport), 1200 Capital Airport Drive, Springfield, IL  62707, for furnishing all labor, materials and equipment and performing all work necessary for:  NORTH AIRPORT ROAD PAVEMENT REHABILITATION
A complete set of bid documents may be obtained from Springfield Reprographics, 1620 S. 5th Street, Springfield, IL  62703 (217) 523-4632, for a non-refundable fee of $25.00.

Contract Time
The Owner has established a contract performance time of 45 calendar days from the date of the Notice To Proceed.  All project work shall be substantially completed within the stated timeframe.  This project is subject to liquidated damages as prescribed within the Project Manual.

Bid Security
Each proposal must be accompanied by a bid guaranty in the amount of ten percent (10%) of the total amount of the bid. 

Bonding Requirements
The successful bidder will be required to furnish separate performance and payment bonds each in the amount equal to one hundred percent (100%) of the contract price at the time of contract execution.

Award of Contract
All proposals submitted in accordance with the instructions presented herein will be subject to evaluation.  Bids may be held by the Airport for a period not to exceed 75 days from the date of the bid opening for the purpose of conducting the bid evaluation.

Award of contract will be based on the lowest aggregate sum proposal submitted from those bidders that are confirmed as being responsive and responsible.  The Springfield Airport Authority reserves the right to waive any informality or irregularity in the bids received, to reject any or all bids in whole or part and to determine the lowest responsible bid.

The award of any contract resulting from this solicitation shall be made by the Board of Commissioners to the Lowest Responsive and Responsible Bidder.  In making this determination, the Springfield Airport Authority will take into account other factors in addition to the lowest dollar bid, such as the Springfield Airport Authority’s past transactions with the bidder, experience of the bidder, adequacy of equipment and personnel, ability to complete performance within a specified time limit and other pertinent considerations.

In the event a bidder has a complaint against the Springfield Airport Authority regarding the manner in which the proposal process has been handled, the complaint must be presented in writing to the Executive Director within forty-eight (48) hours of the opening of the proposals.  The Executive Director will notify the Chairman of the Board of Commissioners of the nature of the complaint.

Provisions:

Modification to the project documents may only be made by written addendum by the Owner or Owner’s authorized Representative.

The proposal must be made on the forms provided within the bound Project Manual.  Bidders must supply all required information prior to the time of bid opening.

Liquidated Damages are provided in the Proposal Form.

The Bidder must supply all information required by the Proposal Form.

Bids must be submitted on the specified Proposal Form and acceptance by the Sponsor shall constitute a Contract.

The proposal which is selected will be based on the lowest aggregate or combination of bids accepted.  The Owner reserves the right to select any one of the bids which best serves the Owner’s interest.

The Contractor is required to comply with wage and labor provisions and to pay minimum wages in accordance with the schedule of wage rates established by the State of Illinois for the county where the work is performed.  The highest rate will be the minimum rate paid for each work classification.

Submittal of Proposals
Additional information and instruction for submittal of a proposal are provided within the Instructions to Bidders.  Envelopes containing bids must be sealed and addressed to:

The Offices of the Abraham Lincoln Capital Airport
1200 Capital Airport Drive
Springfield, IL  62707

The upper left hand corner of the sealed envelope must identify the following information:

CONTRACT PROPOSAL
Bid of   (Name of Contractor)   
for construction improvements at Abraham Lincoln Capital Airport
To be opened at:  9:30 AM, Thursday September 10, 2015

 

 

 

 

 

 

 

 

 